close window |
Total EVAs: | 4 | ||
Total EVA time: | 30h 44m |
No. | Date | Together with | Time | Main tasks and notes |
1 | 05.03.2002 | J. Newman | 7h 17m |
Installing the new port-side array and replacing
one of the four Reaction Wheel Assemblies |
2 | 07.03.2002 | J. Newman | 7h 30m | |
3 | 15.05.2009 | M. Good | 7h 56m |
Changing out three boxes, each containing two of
the telescope's six gyroscopes, and three batteries. |
4 | 17.05.2009 | M. Good | 8h 02m |
Repairing and upgrade the Space Telescope
Imaging Spectrograph and install a stainless steel blanket on Hubble's
exterior. The blankets provide additional thermal protection for some equipment
bays, replacing the existing multi-layer insulation that has degraded over
time. |